- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 24 April 2024
-
Current Status:
Answered by Kate Forbes on 15 May 2024
To ask the Scottish Government whether it will outline any research underpinning the decision to close all VisitScotland information centres.
Answer
VisitScotland’s Strategic Change Programme seeks to ensure that they continue to make the biggest possible positive impact on the visitor economy.
As part of VisitScotland's Strategic Change Programme, a detailed review has considered their role in information provision. VisitScotland's future information strategy is based on research including trends and data that show how visitors plan their trips. As part of the review process, VisitScotland also took into account data related to their iCentre network.
The following key research sources were utilised:
In addition to the above, VisitScotland drew upon the professional knowledge and experience of their staff.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 24 April 2024
-
Current Status:
Answered by Kate Forbes on 15 May 2024
To ask the Scottish Government what assessment it has made of any impact on local economies of the decision to close all VisitScotland information centres.
Answer
VisitScotland has taken the decision to close its iCentre network by March 2026 in response to reduced footfall and demand for information, with data showing that the majority of visitors to Scotland access information ahead of travelling to the country. As this was an operational decision for VisitScotland, the Scottish Government did not conduct an impact assessment.
However, data indicates that the previous phase of iCentre closures in 2018-2019 did not negatively impact the visitor economy. Since 2019, the number of overseas visitors to Scotland has increased by 14%, with the number of tourism businesses increasing by 6%.
VisitScotland continues to support the growth of the visitor economy in every region of Scotland through its marketing activity, support for events, destination development and free-to-access business advice and support programme.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 24 April 2024
-
Current Status:
Answered by Kate Forbes on 15 May 2024
To ask the Scottish Government what consultation took place with (a) staff and (b) trade unions before the decision was made to close all VisitScotland information centres.
Answer
a) A formal staff consultation was not triggered prior to the announcement as there are no compulsory redundancies.
Staff are VisitScotland's priority, and they are engaging with them to discuss their options such as re-skilling, redeployment and voluntary redundancy.
VisitScotland have established a staff engagement programme, which involves every iCentre and allows for both collective and individual engagement and representation throughout the change programme.
b) VisitScotland consulted with Public and Commercial Services (PCS) Union prior to the announcement and continue to work with them during the on-going change programme.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Tuesday, 14 May 2024
-
Current Status:
Answer expected on 30 May 2024
To ask the Scottish Government, further to the answer to question S6W-25868 by Mairi McAllan on 4 March 2024, whether it will provide an update on when in summer 2024 it will publish its Green Industrial Strategy.
Answer
Answer expected on 30 May 2024
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 May 2024
-
Current Status:
Answered by Neil Gray on 14 May 2024
To ask the Scottish Government how many issues NHS Lothian has reported against Consort Healthcare since it took ownership of the Royal Infirmary of Edinburgh.
Answer
NHS Lothian and Consort Healthcare are in an on-going discussion on areas that have been identified where maintenance and improvement is required. This process is continuing, and NHS Lothian regularly meet and discuss all aspects of their administration with Scottish Government officials to enable support to be offered.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 May 2024
-
Current Status:
Answered by Neil Gray on 14 May 2024
To ask the Scottish Government how much money it will have to pay Consort Healthcare when the PFI contract for the Royal Infirmary of Edinburgh ends.
Answer
The project agreement for the RIE was signed in 1998 between NHSL and Consort Healthcare. Consort are responsible for the provision of facilities management and lifecycle maintenance works until the end of the Primary Period in December 2027. The Secondary Period begins automatically following the end of the Primary Period, the exact arrangements for the secondary period, which include the possibility of terminating the agreement, will be determined by the ongoing discussions and decisions taken by NHS Lothian and Consort Healthcare, which have not yet concluded.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Monday, 13 May 2024
-
Current Status:
Answer expected on 29 May 2024
To ask the Scottish Government whether the Graduate Apprenticeship Enhancement Group has been created; who sits on it, and what the expected workstreams are for the group.
Answer
Answer expected on 29 May 2024
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 10 May 2024
-
Current Status:
Answer expected on 28 May 2024
To ask the Scottish Government whether it will provide an update on implementation of the Investor Panel's recommendation 16, and whether such a mechanism has been designed.
Answer
Answer expected on 28 May 2024
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 10 May 2024
-
Current Status:
Answer expected on 28 May 2024
To ask the Scottish Government whether it will provide an update on implementation of the Investor Panel's recommendation 14, and when the results of the exercise will be published.
Answer
Answer expected on 28 May 2024
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 10 May 2024
-
Current Status:
Answer expected on 28 May 2024
To ask the Scottish Government whether it will provide an update on implementation of the Investor Panel's recommendation 9, and when the revised pipeline will be published.
Answer
Answer expected on 28 May 2024