- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 13 January 2022
-
Current Status:
Answered by Ivan McKee on 27 January 2022
To ask the Scottish Government on what date and at what time it contacted Tata Steel after identifying that it may have broken state aid rules while facilitating the sale of the Dalzell steelworks, and whether it will publish any (a) notification and (b) response.
Answer
Scottish Government officials contacted TATA Steel UK on 9 December 2021 to inform the company of its findings concerning the potential presence of State Aid with respect to 2016 transaction. Channels of communication between the Scottish Government and Tata Steel UK to facilitate dialogue remain open but it would not be appropriate to publish the detailed content of these commercially sensitive exchanges.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 13 January 2022
-
Current Status:
Answered by Ivan McKee on 27 January 2022
To ask the Scottish Government what (a) correspondence and (b) meetings it has had with (i) Tata Steel and (ii) Liberty House since identifying that it may have broken state aid rules while facilitating the sale of the Dalzell steelworks, and whether it will publish any (A) minutes and (B) documents regarding this since 1 January 2021.
Answer
Since Ministers were informed of the potential presence of State Aid with respect to its 2016 contract with Tata Steel UK Scottish Government officials have engaged with (a) Tata Steel UK on the following occasions, 9-12-21; 10-12-21; 13-12-21; 14-12-21; 15-12-21; 24-12-21 and 12-1-22 and (b) Liberty Steel-GFG Alliance on the following occasions 9-9-21; 8-11-21; 15-12-21; and 24-1-22.
Channels of communication between the Scottish Government and relevant businesses remain open but it would not be appropriate to publish the detailed content of these commercially sensitive exchanges.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 13 January 2022
-
Current Status:
Answered by Ivan McKee on 27 January 2022
To ask the Scottish Government whether (a) it and (b) Tata Steel has any claim to the land upon which the Dalzell steelworks are situated in the event that Liberty House decides to close the site for reasons other than it ceasing to exist.
Answer
The Scottish Government and TATA Steel do not have any claim on the land upon which the Dalzell steelworks are situated.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 13 January 2022
-
Current Status:
Answered by Ivan McKee on 27 January 2022
To ask the Scottish Government for what reason it necessitated that it take ownership of the Dalzell steelworks for a short period in 2016, and what prevented Tata Steel selling the asset directly to Liberty House.
Answer
Steel production in Scotland had effectively ceased at the time. Our intervention enabled production to recommence and to get skilled Steel workers back to work.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 13 January 2022
-
Current Status:
Answered by Ivan McKee on 27 January 2022
To ask the Scottish Government for what reason the previous owners, Tata Steel, have liabilities in relation to the environmental remediation costs for the site of the Dalzell steelworks, and whether this is typical for the owners of similar former sites.
Answer
The Scottish Government does not assert that Tata Steel has liabilities relating to the environmental remediation costs for the site of the Dalzell steelworks. In the majority of cases potential contaminated land is dealt with routinely through the development planning system or voluntary remediation with the responsibility and costs for carrying out site investigation and any required remediation resting with the site owner / developer.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 13 January 2022
-
Current Status:
Answered by Ivan McKee on 27 January 2022
To ask the Scottish Government what proportion of the total environmental remediation cost of the Dalzell steelworks it would be liable to pay under the agreement it facilitated in 2016 in the event that (a) the site is repurposed as a result of a decision by Liberty Steel and (b) the parent company ceases to exist, and what proportion other parties would be liable for in each circumstance.
Answer
The Scottish Government is not liable for environmental remediation costs.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Wednesday, 05 January 2022
-
Current Status:
Answered by Shona Robison on 25 January 2022
To ask the Scottish Government, further to the debate on motion S6M-02625 (A New Deal for Tenants), how it plans to increase its ambitions for the building of more homes for social rent, and on what date any increased ambition will be announced.
Answer
As set out in our Programme for Government, the Scottish Government has already increased its ambition and commitment to deliver more social homes by increasing our affordable homes target from 100,000 to 110,000 affordable homes by 2032, with 70% of these being for social rent.
Housing to 2040 sets out our long term vision for Housing in Scotland. While a longer-term ambition allows for greater foresight, it does present challenges with predicting how circumstances might change or what unforeseen events might arise. That is why we will carry out a review at the mid-point of the target period, to assess if plans should continue unchanged or be adapted.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Monday, 10 January 2022
-
Current Status:
Answered by Shirley-Anne Somerville on 24 January 2022
To ask the Scottish Government whether a running total of the number of air filter devices that are being used in school classrooms will be published.
Answer
It is for local authorities to exercise their statutory responsibilities and deliver a safe environment for all school users. It is also for local authorities to determine what remedial action is required in their schools, in line with guidance.
The recently announced funding of up to £5 million is in addition to previous funding of £10 million to address issues around ventilation and CO2 monitoring, and on top of £90m of COVID-19 logistics funding.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Monday, 10 January 2022
-
Current Status:
Answered by Shirley-Anne Somerville on 24 January 2022
To ask the Scottish Government whether information on the number of air filters that are being used in school classrooms has been collected for use by the Education Recovery Group.
Answer
It is for local authorities to exercise their statutory responsibilities and deliver a safe environment for all school users. It is also for local authorities to determine what remedial action is required in their schools, in line with guidance.
The recently announced funding of up to £5 million is in addition to previous funding of £10 million to address issues around ventilation and CO2 monitoring, and on top of £90m of COVID-19 logistics funding.
We continue to engage regularly with stakeholders on ventilation, including in the COVID-19 Education Recovery Group.
- Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
-
Date lodged: Thursday, 23 December 2021
-
Current Status:
Answered by Humza Yousaf on 24 January 2022
To ask the Scottish Government, in light of the reported ongoing alterations to the functionality of the NHS Scotland Covid Status app, whether users are (a) notified and (b) required to consent when there is an update to the (i) privacy policy agreement and (ii) personal information that is provided and displayed by the app.
Answer
Privacy notices are updated regularly and accessible via the app and NHS Inform at any point in time.
Consent is sought only when is applicable and consent is not required for the Covid Status app to process data. The legal basis for processing the data in the app is communicated in the privacy notice in detail.