- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Wednesday, 27 April 2005
-
Current Status:
Answered by Nicol Stephen on 12 May 2005
To ask the Scottish Executive, further to the answer to question S2W-15892 by Nicol Stephen on 26 April 2005, (a) which consultants received payment from the sum of £327,735.29, how much was paid to each consultant and what consultancy services were provided, (b) how much of the sum of £152,673.11 was for legal fees and which firms received this payment and (c) which advocate or advocates received payment and how much was paid to each individual.
Answer
The information requested is as follows:
(a) The following consultants received payment from the sum of £327,735.29.
Consultant | Fee Paid | Services Provided |
Glasgow City Council | £9,261.06 | PLI Programme Officer |
Glasgow City Council | £126,740.80 | Design services |
Glasgow City Council | £16,108.60 | Appointed Agent |
Environmental Resources Management | £87,835.01 | Environmental |
Babtie Group | £21,128.54 | Contaminated land |
Bullen Consultants | £5,681.65 | Geotechnical |
SIAS | £60,979.63 | Traffic |
Total | £327,735.29 | |
Notes:
1. The Executive contributes 87.35% to the total cost of the scheme.
2. The remainder of the £152,673.11 is made up of £389.93 for the hire of meeting rooms for consultation with Counsel, £626.11 for copying of papers and productions and £1,310.25 for legal fees incorrectly allocated to PLI costs. The correct cost for Legal Fees and Administration for the PLI is £151,362.86.
(b) £150,346.83 of the £152,673.11 was for legal fees to advocates.
(c) £54,305.50 was paid for the services of David Sheldon, Advocate and £96,041.33 was paid for the services of Raymond Doherty QC.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Tuesday, 26 April 2005
-
Current Status:
Answered by Nicol Stephen on 12 May 2005
To ask the Scottish Executive who bears the risk of delays in relation to the awarding of contracts for the construction of the M74 extension; whether it will place in the Scottish Parliament Information Centre any contract documents providing for such risk, and whether there will be any provision in respect of who bears the financial responsibility for delays caused by (a) protest activity and (b) court proceedings by a third party, such as a judicial review of the decision to proceed, interdict action or other proceedings.
Answer
Our standard Design and Build contract conditions, which are proposed for the construction of the M74 completion scheme, place most of the risk for delays due to unforeseen circumstances on the contractor, since he is best placed to manage the consequence of reprogramming the works.
The Contract documents for the M74 completion scheme are not yet finalised and we will take a view on all relevant risks throughout their development. A copy of the draft M74 contract conditions will be placed in the Scottish Parliament’s Reference Centre once these have been issued to tenderers.
We will proceed to tender once the statutory procedures are secure and will consider with tenderers the appropriate sharing of risk in relation to all potential issues.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Tuesday, 12 April 2005
-
Current Status:
Answered by Nicol Stephen on 5 May 2005
To ask the Scottish Executive, further to the answer to question S2W-15166 by Nicol Stephen on 24 March 2005, what specific role the new regional partnership in the west of Scotland will have in the development, management and monitoring of rail services in its area.
Answer
There are a number of tasks that we propose that the new regional transport partnership in the west of Scotland could perform:
Development – developing project proposals, including producing feasibility studies, developing the business case, through to securing parliamentary powers for infrastructure projects and acting to ensure delivery. It would also involve the development of proposals to improve the passenger journey in rail services and franchise-specific proposals.
Management and monitoring – on behalf of Scottish ministers supporting the national transport agency for Scotland in the day to day franchise management and monitoring activities including performance monitoring, ensuring that the franchisee meets the contractually committed targets and obligations, and analysing trends. These issues will be discussed in greater detail with SPT and the relevant councils over the coming months.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Friday, 08 April 2005
-
Current Status:
Answered by Nicol Stephen on 5 May 2005
To ask the Scottish Executive what the timetable is for the tender process for the provision of the appropriate bus infrastructure to support the use of Smartcards for concessionary travel.
Answer
The timetable is as follows
An OJEU (European Journal procurement notice) for interested parties (EOI) was published on 21 March. Replies close on 28 April. The notice reference number is 2005/S 56-054142.
The planned programme for the remainder of the process is:
w/c 2 May - evaluation of EOIs
w/c 9 May – tender document sign off by Executive
18 May - Document issue to tenderers
13 July - closing date for tenders
w/c 18 July - Tender evaluation
early August - recommendations for inclusion in the framework agreement.
From late August – implementation of installation plans.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Wednesday, 13 April 2005
-
Current Status:
Answered by Nicol Stephen on 5 May 2005
To ask the Scottish Executive what its estimate was of the cost of the public local inquiry on the M74 Special Road (Fullarton Road to West of Kingston Bridge) Orders prior to the inquiry commencing.
Answer
The estimated cost at the start of the PLI was £602,000.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Monday, 25 April 2005
-
Current Status:
Answered by Andy Kerr on 3 May 2005
To ask the Scottish Executive whether it accepts the recommendations in the Calman report in respect of additional undergraduate medical student places and medical schools' admission policies; whether it will make a statement on its position, and when its decision on the report's findings will be announced.
Answer
The Scottish Executive is carefully considering the implications of Sir Kenneth Calmans report and will look to publish its response as soon as possible.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Thursday, 31 March 2005
-
Current Status:
Answered by Nicol Stephen on 28 April 2005
To ask the Scottish Executive whether a decision has been made in respect of which company or companies will provide the completion of access to broadband to rural areas and whether it will publish the terms of any tender awarded for provision of these services and the costs involved.
Answer
A contract was signed on 15 April with BT for the provision of broadband services in 378 exchange areas in Scotland.
An award notice will be published on the website of the Official Journal of the European Communities which will include details of the terms of the contract, including the costs. For information, the public sector is contributing £16.5 million of the total project value of about £30 million.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Monday, 11 April 2005
-
Current Status:
Answered by Margaret Curran on 27 April 2005
To ask the Scottish Executive whether it has a policy of using Scottish rather than English legal terminology in Parliamentary answers and ministerial statements.
Answer
The Scottish Executive’s policy is that parliamentary answers and ministerial statements shouldbe as clear, accurate and helpful as possible; and that any legal terminology whichis used is appropriate in the particular context.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Wednesday, 06 April 2005
-
Current Status:
Answered by Tom McCabe on 27 April 2005
To ask the Scottish Executive whether any of the documents or files containing documents relating to the (a) Holyrood Inquiry and (b) Holyrood Project will be subject to the 30-year rule; if so, whether early release of such documents can be considered under its records management rules and, if so, on what date or dates their early release or, in the case of the first dated thereof, the early release of that document or file can be considered, and whether any person outwith the Scottish Executive will be consulted in relation to such decisions.
Answer
Under the Freedom of Information(Scotland) Act 2002, the 30-year rule no longer applies to any files. The only potentialbars to public access to information held on these files will be particular exemptionswhich might be applied under either FOI or the Data Protection Act 1998.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Wednesday, 06 April 2005
-
Current Status:
Answered by Tom McCabe on 27 April 2005
To ask the Scottish Executive, with regard to its Records Management Manual, whether it will publish a list of lost files as referred to in paragraph 3.9 and give brief details of the subject matter of its lost files since 1999, and prior to that of each lost file of the Scottish Office which it is now responsible for maintaining under the Transfer of Property etc. (Scottish Ministers) Order 1999.
Answer
The list referred to in paragraph3.9 of the Executive’s Records Management Manual is a means to track downfiles which have been mislaid. It is not intended to be an ongoing list of lostfiles. However, we will publish a list of lost files as part of the Scottish Executive Publication Scheme as soon as this can be arranged.