Parliamentary questions can be asked by any MSP to the Scottish Government or the Scottish Parliamentary Corporate Body. The questions provide a means for MSPs to get factual and statistical information.

  • Written questions must be answered within 10 working days (20 working days during recess)
  • Other questions such as Topical, Portfolio, General and First Minister's Question Times are taken in the Chamber

Criathragan Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 4 May 2021
  6. Current session: 13 May 2021 to 11 October 2025
Answer status
Question type

Displaying 2761 questions Show Answers

|

Question reference: S1W-33826

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Thursday, 06 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer, further to his answer to question S1W-9467 on 19 September 2000, whether the matter of the financial costs of the new Parliament building at Holyrood is of greater controversy than it was in March 2000; whether the Scottish Parliamentary Corporate Body (SPCB) will now provide to the public all available financial information; what the reasons are for the position on this matter in the light of the position given in the answer to question S1W-9467; whether it will continue to be the position that documents in relation to the package awarded to Flour City Architectural Metals (UK) Ltd will not be disclosed; if so, whether the SPCB will review this position and what the reasons are for the position on this matter, and, if such reasons relate to potential prejudice to any legal action, how any such action could be prejudiced or damaged by such disclosure, given that the legal liability will already have been set and cannot be in any way altered by such disclosure.

Question reference: S1W-33930

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Monday, 10 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer, further to his answer to question S1W-21634 on 22 January 2002, whether the summaries given in the Holyrood Progress Group's newsletters of the group's question and answer sessions have been (a) accurate, (b) impartial and (c) complete and what plans it has for such summaries in future to be prepared by the Parliament's official reporters to ensure accuracy, impartiality and completeness.

Question reference: S1W-33932

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Monday, 10 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer whether there was any regular arrangement for meetings between representatives of Bovis Lend Lease and Flour City Architectural Metals (UK) Ltd (FCAM) about the progress of FCAM in relation to fulfilling its obligations under the works package awarded to it; on what dates any such meetings took place or were due to take place, and whether any minutes of, or other documents showing the matters discussed at, such meetings will be placed in the Scottish Parliament Information Centre.

Question reference: S1W-33947

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Tuesday, 11 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer which works package contracts let in relation to the Holyrood project have (a) been completed and (b) not been completed and what the reasons are for any such contracts not having been completed; what the (i) original estimated cost was and (ii) current estimated cost is of any uncompleted contracts, and what the estimated date of completion is of each such contract.

Question reference: S1W-33946

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Tuesday, 11 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer, further to his answer to question S1W-18874 on 12 October 2001, whether any further work has been carried out by other contractors on (a) work initially carried out by Flour City Architectural Metals (UK) Ltd (FCAM) and (b) design and specialist cladding services provided by FCAM and, if so, whether he will give full details of (i) the services provided and (ii) the total cost of such services.

Question reference: S1W-33949

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Tuesday, 11 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer, with regard to paragraph 14 of The 2001/02 Audit of the Scottish Parliamentary Corporate Body by the Auditor General for Scotland, when the construction managers were first alerted by any member, employee or representative of the Bovis group of companies to any problems and difficulties in respect of the Canary Wharf project that was undertaken by Flour City Architectural Metals (UK) Ltd (FCAM) and terminated in August 2001; whether information received in respect of this matter was passed on to any member of the Holyrood project team, the Holyrood Progress Group or the Scottish Parliamentary Corporate Body and, if so, on what date, and whether, prior to award of the contract, references were received from any other member of the Bovis group and, if so, from which member and in respect of which other contracts undertaken by FCAM or any other member of the Flour City International group of companies.

Question reference: S1W-33948

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Tuesday, 11 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer, with regard to paragraphs 6 and 7 of The 2001/02 Audit of the Scottish Parliamentary Corporate Body by the Auditor General for Scotland, when the advert or adverts were placed for the tender of the cladding and windows package for the MSP block of the Holyrood project; whether copies of such adverts will be placed in the Scottish Parliament Information Centre, and on what date, and by what means, the two bids received in respect of this package were submitted.

Question reference: S1W-33945

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Tuesday, 11 February 2003
  • Current Status: Answered by David Steel on 12 February 2003

To ask the Presiding Officer whether companies based in Scotland that expressed an interest in obtaining works packages, or a part thereof, in respect of the Holyrood project were treated fairly and properly; whether the Scottish Parliamentary Corporate Body (SPCB) has been kept fully aware of all potential involvement by Scottish companies, and whether the SPCB will now carry out a review in respect of these matters.

Question reference: S1W-33695

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Tuesday, 04 February 2003
  • Current Status: Answered by Frank McAveety on 11 February 2003

To ask the Scottish Executive into which category of care service, as set out in the draft statutory instrument attached as appendix A to The Regulation of Care (Scotland) Act 2001 - Regulation of Care Services by the Scottish Commission for the Regulation of Care: Proposals for Maximum Fees to be set by Scottish Ministers for 2003-04: Consultation Paper, organisations such as Crossroads would fall; what registration fees such bodies would pay, and whether such bodies would need to pay any annual continuing charge.

Question reference: S1W-33436

  • Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
  • Date lodged: Monday, 27 January 2003
  • Current Status: Answered by David Steel on 10 February 2003

To ask the Presiding Officer what the installation cost was of each window in the MSP block west elevation of the new Parliament building at Holyrood under the (a) Flour City contract and (b) current contract.